What We Achieved

Cronin Group successfully delivered the safe relocation, transport, offload, and final positioning of 3 tonne critical x-ray screening equipment for FedEx during the move to their new facility at Horizon Logistics Park.

The project was completed safely, on time, and with minimal disruption to operations.

How We Delivered

Our Machinery Moving team provided a fully coordinated Delivery, Offload & Positioning (DOP) solution including:

  • Disconnection support
  • Specialist forklift handling
  • Secure loading and transport
  • Precision offload and positioning
  • Final placement in operational areas

Every stage was carefully planned to protect sensitive equipment and maintain programme certainty.

The Result

  • Zero equipment damage
  • Safe and efficient relocation
  • Minimal operational disruption
  • On-time project completion

Key KPI Performance

KPI Result
On-Time Delivery 100%
Equipment Damage 0
Safety Incidents 0
Operational Disruption Minimal